08/12/2009, an inspection team finish the first inspection of MT-P Inverter power cubicles for rail transportation system, the inspection last for two days and the inspection team insist by: Mr.Horst the expert from Germen SIMENS, Mr.Li the chief inspector from Tongye, Mr.Wu the quality manager from Tongye, IWE of our company and related responsible person. The inspection include: check the material certificates, WPS, work specimen, SOP and other related documents; the welding seam, overall check the painting and welding seam of the cubicles.
After two days strict inspect, Mr.Horst, the expert come from Germen SIMENS finaly judged the “MT-P Inverter power cubicles for rail transportation system” which inspected this time meet all the customers quality and technical requirements, the product is qualified.
The successfully passed the inspection this time mines our company have reached the working ability of EN15085 CL1 products. Meanwhile, it mines our welding technical have reached the international advanced level in the same industry. It also promote our competitive strength in the same industry.
After the event, general manager organize a review meeting, certainly the work results and indicate that we need to enhance the technical training of welding team and other technical teams. Laid the solid foundation for the further development of the company.
ShenZhen JingGong Mechanism & Electric Equipment Co., Ltd
10/12/2009
|